In the Matter of the Application of Union Electric )
Company, d/b/a Ameren Missouri for Permission and )
Approval and a Certificate of Public Convenience and )
Necessity Authorizing it to Construct,
Install, Own, ) File No. EA-2012-0281
Operate, Maintain, and Otherwise Control and )
Manage a Utility Waste Landfill and Related Facilities )
At its Labadie Energy Center. )
Issue Date: February
25, 2013 Effective
Date: February 25, 2013
On January 24, 2013, Union Electric Company d/b/a Ameren Missouri filed an application seeking a certificate of convenience and necessity from the Commission to expand the boundaries of its Labadie Energy Center to permit the construction and operation of a utility waste landfill. To begin moving this case to resolution, the Commission will schedule a prehearing conference at which the parties will be directed to prepare and submit a proposed procedural schedule.
THE COMMISSION ORDERS THAT:
1. A prehearing conference is scheduled for March 11, 2013,
at 10:00 a.m., at the Commission’s office at the
2. This order shall become effective upon issuance.
( S E A L )
Morris
L. Woodruff, Chief Regulatory Law
Judge,
by delegation of authority
pursuant
to Section 386.240, RSMo 2000.
Dated
at
on this 25th
day of February, 2013.