BEFORE THE PUBLIC SERVICE COMMISSION

OF THE STATE OF MISSOURI

 

In the Matter of                                                    )

Kansas City Power & Light Company’s                  )               File No. ER-2012-0174

Request for Authority to Implement                       )       Tracking No. YE-2012-0404

A General Rate Increase for Electric Service         )

 

and

 

In the Matter of                                                    )

KCP&L Greater Missouri Operations Company’s    )               File No. ER-2012-0175

Request for Authority to Implement                       )       Tracking No. YE-2012-0405

General Rate Increase for Electric Service             )

                                       

ORDER EXCUSING ALL PARTIES ON

WEDNESDAY, OCTOBER 24, 2012, AND THURSDAY, OCTOBER 25, 2012

 

Issue Date:  October 23, 2012                                              Effective Date:  October 23, 2012

 

          The Missouri Public Service Commission is granting the parties’ request to recess the evidentiary hearing for the next two days following the date of this order.  

          THE COMMISSION ORDERS THAT:

1.          The request described in the body of this order is granted. 

2.          All parties, counsel, and witnesses are excused from appearing at the evidentiary hearing on

a.     Wednesday, October 24, 2012; and

b.     Thursday, October 25, 2012.

3.          This order is effective immediately upon issuance.

BY THE COMMISSION

 

 

( S E A L )

 

Steven C. Reed

Secretary

                                                                                                                                                                                                  

Daniel Jordan, Senior Regulatory Law Judge,

by delegation of authority pursuant

to Section 386.240, RSMo 2000.

 

Dated at Jefferson City, Missouri,

on this 24th day of October, 2012.