BEFORE THE PUBLIC SERVICE COMMISSION
OF THE STATE OF
Earth Island Institute d/b/a )
Renew Missouri, et al. )
)
Complainants, )
)
v. ) File
No. EC-2013-0378
)
The Empire District Electric Company )
)
Respondent. )
Issue Date: January 31, 2013
The Empire District Electric Company
602 S. Joplin Ave.
Joplin, Missouri 64801
CERTIFIED MAIL
On January 30,
2013, Earth Island Institute d/b/a Renew Missouri; Missouri Coalition for the
Environment; Missouri Solar Energy Industries Association; Wind on the Wires;
The Alternative Energy Company, LLC; StraightUp
Solar; and Missouri Solar Applications LLC filed a complaint with the Commission
against The Empire District Electric Company, a copy of which is enclosed. Commission Rule 4 CSR 240‑2.070
allows the Respondent 30 days from the date of this notice to file an
answer or to file notice that the complaint has been satisfied. Thirty days from this date is March 2, 2013,
but since that is a Saturday, The Empire District Electric Company must file
its answer no later than Monday, March 4, 2013.
This complaint
is a contested case. As required by section 536.067(2)(f), RSMo 2000, the
Commission informs the parties that the Commission’s provisions governing procedures
before the Commission, including provisions relating to discovery are found at
Commission Rule Chapter 4 CSR 240-2.
BY THE COMMISSION
(S E A L)
Shelley Brueggemann
Acting Secretary
Dated at Jefferson City, Missouri,
on this 31st day of January, 2013.